Abstract

This is the first interim report on the Cost of Tendering component of the Best Value project. This report provides some insight from ‘cost of tendering’ literature and discussions with CRC partners. With the completion of this scoping project, sufficient understanding will be developed to determine the need for more detailed research. This scoping project does not intend to provide guidance for the way to change the tendering process, although a need will be demonstrated for control and reduction of cost of tendering.

Impact and interest:

Citation counts are sourced monthly from Scopus and Web of Science® citation databases.

These databases contain citations from different subsets of available publications and different time periods and thus the citation count from each is usually different. Some works are not in either database and no count is displayed. Scopus includes citations from articles published in 1996 onwards, and Web of Science® generally from 1980 onwards.

Citations counts from the Google Scholar™ indexing service can be viewed at the linked Google Scholar™ search.

Full-text downloads:

122 since deposited on 26 Aug 2009
7 in the past twelve months

Full-text downloads displays the total number of times this work’s files (e.g., a PDF) have been downloaded from QUT ePrints as well as the number of downloads in the previous 365 days. The count includes downloads for all files if a work has more than one.

ID Code: 27072
Item Type: Report
Refereed: No
Keywords: CRC for Construction Innovation, Program C : Delivery Management of Built Assets , Project 2002-035-C : Linking Best-Value Procurement Assessment to Outcome Performance Indicators
Divisions: Current > Research Centres > CRC Construction Innovation
Copyright Owner: Copyright 2008 Icon.Net Pty Ltd
Copyright Statement: The Participants of the CRC for Construction Innovation have delegated authority to the CEO of the CRC to give Participants permission to publish material created by the CRC for Construction Innovation. This delegation is contained in Clause 30 of the Agreement for the Establishment and Operation of the Cooperative Research Centre for Construction Innovation. The CEO of the CRC for Construction Innovation gives permission to the Queensland University of Technology to publish the papers/publications provided in the collection in QUT ePrints provided that the publications are published in full. Icon.Net Pty Ltd retains copyright to the publications. Any other usage is prohibited without the express permission of the CEO of the CRC. The CRC warrants that Icon.Net Pty Ltd holds copyright to all papers/reports/publications produced by the CRC for Construction Innovation.