Contractor Risks in Design, Novate and Construct Contracts

Ng, S. Thomas & Skitmore, Martin (2002) Contractor Risks in Design, Novate and Construct Contracts. International Journal of Project Management, 20(2), pp. 119-126.

View at publisher

Abstract

The Design, Novate and Construct (DN&C) system is becoming an increasingly popular method of construction procurement. In the DN&C system, the contractual rights and liabilities of the design team are transferred to the contractor once appointed. This makes DN&C a very attractive procurement option for the client but leaves contractors with the problem of identifying and managing the extra risks involved. The aim of this paper is to identify these risks.

The results are described of a series of interviews with construction projects managers experienced in DN&C work. These show that the major risks to contractors in DN&C are concerned with (i) the novated design team’s ability to perform, (ii) the lack of design team fees allocated to the post-novation phase, (iii) the working relationship with the novated design team, and (iv) the timing of the novation. It was also found that contractors had insufficient time during the bid preparation period to check the design produced by the novated design team.

Impact and interest:

17 citations in Scopus
Search Google Scholar™

Citation countsare sourced monthly from Scopus and Web of Science® citation databases.

These databases contain citations from different subsets of available publications and different time periods and thus the citation count from each is usually different. Some works are not in either database and no count is displayed. Scopus includes citations from articles published in 1996 onwards, and Web of Science® generally from 1980 onwards.

Citations counts from the Google Scholar™ indexing service can be viewed at the linked Google Scholar™ search.

Full-text downloads:

1,929 since deposited on 19 May 2006
470 in the past twelve months

Full-text downloadsdisplays the total number of times this work’s files (e.g., a PDF) have been downloaded from QUT ePrints as well as the number of downloads in the previous 365 days. The count includes downloads for all files if a work has more than one.

ID Code: 4230
Item Type: Journal Article
Keywords: Contractor’s risk, design, novate and construct, procurement system
DOI: 10.1016/S0263-7863(00)00051-X
ISSN: 0263-7863
Subjects: Australian and New Zealand Standard Research Classification > BUILT ENVIRONMENT AND DESIGN (120000) > BUILDING (120200) > Building Construction Management and Project Planning (120201)
Divisions: Past > QUT Faculties & Divisions > Faculty of Built Environment and Engineering
Copyright Owner: Copyright 2002 Elsevier
Copyright Statement: Reproduced in accordance with the copyright policy of the publisher.
Deposited On: 19 May 2006
Last Modified: 09 Jun 2010 22:32

Export: EndNote | Dublin Core | BibTeX

Repository Staff Only: item control page