Human effects in early stage construction contract price forecasting

Skitmore, Martin, Stradling, Steven G., & Tuohy, Alan P. (1994) Human effects in early stage construction contract price forecasting. IEEE Transactions on Engineering Management, 41(1), pp. 29-40.

View at publisher

Abstract

This paper describes a postal survey of UK Quantity Surveyors to relate human factors, such as experience and personality, to conceptual estimating expertise. Composite variables were derived by factor analysis and examined against estimates of average national prices for several types of building.

It is shown that expertise is very much of a project specific nature and does not extend in a simplistic way to projects outside the defined domain and that estimators must exercise of great caution when undertaking work even slightly outside their regular activities. Different building types demand different emphasis and special attention is drawn to the complexity of the project, the degree of services content, and particular sub-market conditions. The easiest projects to estimate appear to be industrial (factories) and residential (houses) with offices being the hardest, probably due to the wider variety of design and quality options in the latter. 'Knowledge and 'care' are identified as the most crucial attributes of good estimators.

A few myths are also dispelled. Geographical location, for instance, was found not to be a major issue. Similarly, there was no evidence of any 'X' factor whereby individuals can claim any mystical in-born talent. The indications are that good estimators have exactly the same attributes as good gamblers - they do their research selectively and thoroughly, think carefully and concentrate on what they know best.

Impact and interest:

4 citations in Web of Science®
Search Google Scholar™

Citation countsare sourced monthly from Scopus and Web of Science® citation databases.

These databases contain citations from different subsets of available publications and different time periods and thus the citation count from each is usually different. Some works are not in either database and no count is displayed. Scopus includes citations from articles published in 1996 onwards, and Web of Science® generally from 1980 onwards.

Citations counts from the Google Scholar™ indexing service can be viewed at the linked Google Scholar™ search.

Full-text downloads:

254 since deposited on 09 Jun 2006
10 in the past twelve months

Full-text downloadsdisplays the total number of times this work’s files (e.g., a PDF) have been downloaded from QUT ePrints as well as the number of downloads in the previous 365 days. The count includes downloads for all files if a work has more than one.

ID Code: 4436
Item Type: Journal Article
Keywords: Estimating, human factors, expertise, accuracy, early stage design
DOI: 10.1109/17.286323
ISSN: 0018-9391
Subjects: Australian and New Zealand Standard Research Classification > BUILT ENVIRONMENT AND DESIGN (120000) > BUILDING (120200) > Quantity Surveying (120203)
Divisions: Past > QUT Faculties & Divisions > Faculty of Built Environment and Engineering
Copyright Owner: Copyright 1994 IEEE
Copyright Statement: Personal use of this material is permitted. However, permission to reprint/republish this material for advertising or promotional purposes or for creating new collective works for resale or redistribution to servers or lists, or to reuse any copyrighted component of this work in other works must be obtained from the IEEE.
Deposited On: 09 Jun 2006
Last Modified: 09 Jun 2010 22:32

Export: EndNote | Dublin Core | BibTeX

Repository Staff Only: item control page